How to Prepare a Unitized Curtain Wall RFQ: A Complete Buyer Checklist
Introduction: Build a Comparable RFQ Package
A unitized curtain wall RFQ is more than a request for a lump-sum price. It is a controlled information package that tells suppliers what project, system, documents, materials, performance requirements, responsibilities, delivery conditions, and commercial assumptions they are expected to address.
A useful unitized curtain wall RFQ checklist should include a project brief, drawing and revision register, facade elevations and details, panel/module schedule, glass and infill schedule, materials and finishes, performance and testing requirements, engineering and QA/QC responsibilities, factory and logistics scope, delivery and installation boundaries, programme, commercial assumptions, and a standard response format.
Require every bidder to mark items as included, optional, excluded, or subject to confirmation. Record assumptions, alternatives, deviations, and open questions before comparing totals. A complete package improves clarity and comparability; it does not guarantee the lowest price, compliance, performance, or delivery date.
This checklist is a flexible procurement framework, not a universal legal or technical form. Adapt it to your project documents, procurement route, contract, local requirements, and design stage. For why technical and commercial inputs change a quotation, see our guide to the factors that affect unitized curtain wall pricing.
What Should Be Included in a Unitized Curtain Wall RFQ?
At minimum, assemble the following package before requesting comparable supplier quotations:
| RFQ section | Information to provide or request | Why it matters | Owner/status |
|---|---|---|---|
| Project brief | Project name, location, building type, procurement route, package boundary, contacts, issue date, and bid deadline | Establishes commercial and geographic context | Buyer / to be confirmed |
| Document register | Drawing and specification numbers, revisions, dates, formats, status, and addenda | Prevents bidders from pricing different information | Buyer / controlled |
| Facade scope | Areas, elevations, grids, sections, details, openings, non-unitized zones, and interfaces | Defines what is inside and outside the package | Buyer and design team |
| Panel schedule | Panel marks, locations, dimensions, quantities, repetition, custom conditions, corners, transitions, and weight where known | Converts facade geometry into a controllable schedule | Buyer / design team |
| Glass and infill | Make-up, thickness, coatings, panels, spandrels, openings, visual and performance requirements | Establishes the material basis | Design team / to be confirmed |
| Performance and testing | Applicable project requirements, mockups, tests, acceptance criteria, reports, and retesting | Makes verification scope explicit | Qualified professionals |
| Responsibility matrix | Design, calculations, BIM, shop drawings, testing, QA/QC, logistics, installation, replacement, and handover | Prevents hidden scope gaps | Buyer with project team |
| Logistics and site | Packaging, delivery point, customs, unloading, storage, lifting, access, and installation boundary | Makes delivery bases comparable | Buyer / supplier to confirm |
| Commercial schedule | Quantity, phases, programme, currency, validity, taxes, duties, payment, alternatives, allowances, assumptions, and exclusions | Makes bids levelable | Buyer |
| Response format | Line-item pricing, status matrix, technical response, programme, documents, and open questions | Produces normalized supplier responses | Buyer |
The package should also state whether you want a supply-only quotation, delivered-to-site quotation, supply-and-installation quotation, design-assist pricing, delegated-design pricing, budget estimate, or base bid with alternatives. If bidders may propose different systems, say so explicitly and define how alternatives will be reviewed.
Step 1: Define the Project Brief and Procurement Route
Project Information
State the project name, location, building type, intended use, design stage, facade package, buyer entity, project contacts, issue date, question deadline, bid deadline, and required response format. Include the destination and delivery point if the quotation may involve cross-border supply.
The brief should describe the planning context without assuming a particular system is suitable. A high-rise office project may require clear floor-to-floor conditions, repeated modules, lifting assumptions, and installation interfaces. A mixed-use project may require separate podium, tower, entrance, corner, and transition information. A public or institutional project may require defined review, testing, traceability, and handover documents.
Procurement Route
Tell bidders which procurement route the RFQ represents:
- Supply-only
- Delivered-to-site
- Supply and installation
- Design-assist
- Delegated design
- Early budget estimate
- Competitive base bid with approved alternatives
- Another project-specific route
Do not assume that all bidders interpret "unitized curtain wall quotation" the same way. If design information is incomplete, identify expected allowances, deliverables, and design responsibilities. If alternative systems are permitted, state the required technical submission and comparison basis.
Package Boundary and Response Deadline
Define the boundary between the curtain wall package and adjacent work. State whether doors, louvers, shading, stone, metal panels, waterproofing, fire stopping, structure, access equipment, and interior finishes are included, coordinated, supplied by others, or excluded.
Include the response deadline, clarification process, required file format, quotation validity, and contact for technical questions. Your project's contract and procurement policy take precedence over this checklist.
Step 2: Create a Controlled Drawing and Document Register
Drawing Register
A controlled register helps each bidder price the same revision. List, as applicable:
- General arrangement drawings
- Facade elevations and grids
- Floor plans, sections, and enlarged details
- Typical head, sill, jamb, stack-joint, and slab-edge details
- Internal and external corners
- Podium/tower, roof, parapet, and base conditions
- Transitions and movement-joint details
- Interfaces with structure, waterproofing, fire stopping, doors, louvers, shading, and other facade systems
- Specifications, schedules, area take-offs, and non-unitized zones
- Drawing numbers, revision letters, issue dates, and addenda
- File formats, model coordinates, and technical-query contacts
Each row should show the document number, title, revision, issue date, format, status, and bidder action. If a document is missing, mark it as an open issue rather than letting bidders make different silent assumptions.
Required Details and Interfaces
Elevations alone may not show the information needed to understand panel marks, slab edges, corners, drainage, movement, openings, or adjacent packages. Attach the details that define typical and non-typical conditions, and identify any area still at design-development stage.
Also list the supplier documents you expect back, such as product data, CAD details, specifications, installation or assembly information, maintenance information, certificates, and test reports. Define these per project rather than assuming every supplier provides an identical package.
Revision and Addenda Control
State which revision forms the pricing basis. Require bidders to confirm the drawing register and list any addenda or clarification responses used. Suppliers should identify discrepancies, missing dimensions, unpriced assumptions, and conflicts between drawings and specifications.
Do not compare a quotation based on an earlier elevation with one based on a later panel schedule as if the scope were identical. If information changes during the RFQ, issue the same controlled addendum to all bidders.
Step 3: Issue the Elevations, Details, and Facade Scope
Typical Details
Mark the typical grid, floor-to-floor condition, slab edge, head, sill, jamb, stack joint, drainage path, glazing plane, and connection intent in the quotation documents. Your qualified design professionals must define and review structural, water, fire, movement, and other technical requirements.
Non-Typical and Interface Conditions
Mark internal and external corners, podium/tower transitions, roof and parapet conditions, base interfaces, slopes, curves, irregular grids, openings, fins, shading, louvers, doors, stone, metal panels, BIPV, and movement joints. Show how these conditions relate to the unitized package and adjacent work.
For each non-typical condition, ask the bidder to state whether it is included, optional, excluded, or subject to confirmation. Request the relevant detail, panel mark, material basis, engineering responsibility, testing assumption, and installation boundary.
Areas Outside the Unitized Package
Identify areas that are not unitized curtain wall, such as non-unitized infill, special entrance assemblies, opaque panels, local repairs, adjacent facade systems, or work by others. A clear exclusion is more useful than an area that disappears from the quotation without explanation.
Step 4: Build the Panel/Module Schedule
What the Schedule Should Contain
A panel or module schedule translates the elevations into a controlled list of panel marks, locations, quantities, materials, dimensions, repetition, and handling assumptions. Include, as applicable:
- Panel mark and elevation or location
- Typical, repeated, mirrored, and unique status
- Nominal width and height
- Floor-to-floor and slab-edge conditions
- Glass and infill type
- Openings, spandrels, fins, shading, and attachments
- Internal and external corners
- Podium/tower and other transition modules
- Estimated weight where known
- Packing, lifting, access, and storage constraints
- Quantities by building, elevation, phase, and delivery batch
Typical Versus Custom Panels
Separate standard repeated panels from custom or design-development panels. If a panel is not fully defined, label it as an allowance, design-development item, or subject to confirmation. Do not invite bidders to make different assumptions and then treat their totals as directly comparable.
Dimensions, Weight, and Tolerances
Provide typical, minimum, and maximum width and height, floor-to-floor constraints, estimated weight and center of gravity where known, relevant tolerances, attachment conditions, and handling restrictions. Ask bidders to identify any dimensions, weights, tolerances, or lifting conditions they have assumed.
The schedule should also show standard-module count, unique-panel count, repetition ratio, panel quantities, and delivery batches. If the design is still developing, identify the design responsibility and change-control process rather than hiding uncertainty inside a lump sum.
Panel schedule template:
| Field | Buyer input or supplier response |
|---|---|
| Panel mark and location | Elevation, grid, floor, zone, and building |
| Status | Typical, repeated, mirrored, unique, allowance, or subject to confirmation |
| Dimensions | Width, height, floor-to-floor, and slab-edge conditions |
| Glazing/infill | Glass make-up, spandrel, metal panel, opaque infill, or other basis |
| Openings and attachments | Doors, vents, fins, shading, brackets, and interfaces |
| Geometry | Corners, transitions, slopes, curves, or irregular forms |
| Quantity | By building, elevation, phase, and delivery batch |
| Handling | Weight where known, packing, lifting, access, and storage assumptions |
| Supplier qualification | Deviation, assumption, alternative, or clarification |
Step 5: Define Glass, Infill, Materials, Finishes, and Hardware
Glass and Infill Schedule
State the glass make-up, nominal thickness, coatings, interlayers, spacer and gas assumptions where relevant, visual criteria, sample requirements, and performance targets. Identify insulated, laminated, monolithic, spandrel, metal-panel, opaque, or other infill configurations.
Also state pane size, weight, edge treatment, color, frit, reflectance, ceramic coating, safety criteria, and whether factory glazing or sealing is included. Do not rely on broad descriptions such as "double glazing" or "high performance" without a defined schedule.
Profiles, Thermal Breaks, and Accessories
Define the aluminum profile basis, profile depth, reinforcement, thermal-break approach, drainage, gaskets, sealants, isolators, anchors, brackets, fasteners, flashings, pressure plates, cover caps, and hardware. Ask bidders to identify their proposed product basis and any approved-equivalent or alternative item.
The screening fields on our Unitized Curtain Wall Systems page (system depth, glazing method, glass plane, glazing installation, and infill type) are a useful starting list for these RFQ questions.
Finishes, Samples, and Alternatives
State whether the finish is painted, anodized, fluoropolymer, or another specified system. Include color, gloss, texture, dual finishes, batch consistency, sample approval, mockup requirements, and replacement assumptions.
Set an approved-alternative procedure. Require bidders to list substitutions separately from the base bid, explain technical differences, submit product data and samples where requested, and state any effect on programme, responsibility, testing, or maintenance. Do not treat an unmarked alternative as equivalent to the specified basis.
Step 6: State Performance, Codes, Testing, and Mockup Requirements
Performance Brief
The RFQ should identify the project's applicable design requirements without assuming compliance. As applicable, define:
- Wind and structural design basis
- Movement, seismic, or interstory-drift requirements
- Air, water, and thermal objectives
- Acoustic, solar-control, condensation, safety, or fire requirements
- Authority or design-review requirements
- Mockup type and representative configuration
- Laboratory and field test expectations
- Test agency, witnessing, reports, and retesting
- Corrective work and acceptance criteria
- The party responsible for defining, designing, submitting, reviewing, and accepting each requirement
Mockup and Test Plan
State whether a pre-construction laboratory mockup, field mockup, or both are required. Identify the representative specimen, test method, agency, witnessing, report format, acceptance criteria, retesting, and responsibility for changes after a failed or revised mockup.
ASTM E2099-23 covers pre-construction laboratory mockup design and construction, observation, testing, evaluation, documentation, and coordination for exterior wall systems. ASTM E331-00(2023) covers water-penetration testing of curtain walls under a uniform static air-pressure difference. Name the specific methods your project requires rather than citing standards generally.
Acceptance Criteria and Professional Review
Ask the project team and bidders to distinguish design requirements, test methods, acceptance criteria, test reports, corrective actions, and final approvals. Mentioning ASTM, AAMA/FGIA, EN, or local codes is not a substitute for a configuration-specific test plan, report, or qualified review.
Step 7: Assign Engineering, BIM, Shop Drawings, QA/QC, and Submittals
Engineering and Calculations
Use a responsibility matrix to assign design assistance, delegated design, calculations, analysis, system details, interface details, and revisions. State whether the supplier is expected to review buyer information, develop details, produce calculations, or only manufacture to approved documents.
Our Curtain Wall Design & Budget Planning service covers engineering design, shop drawings, structural calculations, system details, material schedules, installation planning, and BIM coordination. Whichever supplier you use, ask them to list which of these deliverables their quotation includes.
BIM and Drawing Deliverables
Define BIM authoring, model detail level, file format, clash coordination, model exchanges, panel schedules, bills of materials, shop drawings, fabrication drawings, installation details, revision limits, and approval steps. State who owns the model, who coordinates interfaces, and how changes are instructed and recorded.
QA/QC, Traceability, and Handover
Request a QA/QC response covering:
- Assembly, glazing, sealing, and labeling
- Inspection points and release criteria
- Material certificates and batch traceability
- Finish and color controls
- Dimensional checks and panel tolerances
- Sealant and gasket compatibility records where applicable
- Nonconformance, rework, and replacement procedures
- Packaging inspection and damage prevention
- Site acceptance and installation inspection
- Reports, photographs, checklists, manuals, and handover records
Require each bidder to classify these deliverables as included, optional, excluded, or subject to confirmation.
Step 8: Define Factory Assembly, Packaging, Logistics, Delivery, and Installation
Factory Scope and Quality Release
State whether the supplier is responsible for assembly, factory glazing, sealing, inspection, labeling, storage, rework, release criteria, batch identification, and traceability. Define the boundary between factory QA/QC and site acceptance.
FOWALL's unitized panels are factory-glazed, so we recommend stating in the RFQ exactly where factory release ends and site acceptance begins.
Packaging and Delivery Point
Define packaging format and protection for glass, corners, fins, and custom units. State loading, containerization, transport, insurance, customs, duties, taxes, loss or damage responsibility, delivery point, port, inland route, unloading, storage, and weather protection.
If Incoterms are used, identify the selected term and the practical responsibility boundary. If another allocation is used, describe it in plain language. Have your commercial and legal teams review the final terms.
Lifting, Installation, and Handover
State hoist, crane, lifting-equipment, floor-access, staging, storage, and site-readiness assumptions. Clarify installation labor, supervision, training, technical support, site adjustments, damaged-unit replacement, re-delivery, handover, and maintenance documentation.
Supply-only, delivered-to-site, and installed quotations are not comparable unless these boundaries are explicit. Require the supplier to mark each item as included, optional, excluded, or subject to confirmation.
Step 9: Add the Programme and Commercial Schedule
Quantity and Phases
Provide facade area, panel count, buildings, elevations, phases, standard-to-unique panel ratio, and delivery batches. Separate unitized areas from non-unitized areas and identify any allowance or design-development quantity.
Programme and Site Readiness
List submittal, approval, fabrication, mockup, testing, delivery, floor release, installation, and handover milestones. State site-readiness assumptions, installation windows, storage limits, delivery batches, and dependencies. Ask bidders for a project-specific programme with assumptions rather than a generic lead-time statement.
Currency, Validity, Taxes, Duties, and Exclusions
Include response date, quotation validity, currency, taxes, duties, insurance, escalation, payment terms, retention or bonds where applicable, alternatives, allowances, provisional items, unit rates, warranty and service clauses, and open questions. These conditions depend on your project, contract, jurisdiction, and procurement policy.
What Should a Unitized Curtain Wall Supplier Response Include?
Require every bidder to return the same structure:
- Bid identification — Project name, RFQ number, bidder legal entity, contact, revision used, and authorized signatory.
- Scope confirmation — Confirmed system, elevations, panel schedule, materials, factory work, delivery point, and installation boundary.
- Pricing schedule — Base bid, alternatives, allowances, unit rates, taxes/duties where applicable, currency, and validity.
- Included/optional/excluded/confirm matrix — One line for each technical, logistics, installation, testing, and commercial item.
- Technical response — Proposed system, glass/infill, finishes, interfaces, drawings, calculations, BIM, testing, and QA/QC documents.
- Programme — Design/submittal, mockup, testing, fabrication, delivery, and installation milestones.
- Assumptions and qualifications — Deviations, missing information, allowances, alternatives, dependencies, and exclusions.
- Clarification register — Question, RFQ reference, requested answer, cost/programme effect, and response deadline.
- Document list — Product data, drawings, calculations, test reports, samples, certificates, manuals, and proposed submittals.
A lump sum with no scope schedule, assumptions, exclusions, or open questions should be clarified before it is compared with structured responses.
Which Clarification Questions Should Be Asked Before Bid Leveling?
Ask the same questions of every bidder and keep an auditable record:
- Which drawing and specification revisions form the basis of your offer?
- Have all addenda and RFQ responses been included?
- Which areas are excluded or treated as non-unitized?
- Which panel marks, dimensions, tolerances, or interfaces are assumptions?
- What glass, infill, profile, finish, gasket, sealant, anchor, and hardware basis has been priced?
- Does the offer include calculations, shop drawings, BIM, design revisions, and submittals?
- Which mockups, tests, test reports, witnessing, retesting, and corrective work are included?
- Is factory glazing, sealing, inspection, storage, rework, labeling, and release included?
- What are the packaging, delivery point, customs, unloading, lifting, storage, and site-access assumptions?
- Is installation included, excluded, or limited to supervision or technical support?
- What taxes, duties, allowances, alternatives, escalation, payment, and validity assumptions apply?
- What is the effect of each clarification on price, programme, and responsibility?
Record answers in a clarification register or addendum. Where procurement rules require common information, issue material clarifications to all bidders.
Clarification register template:
| Question | RFQ reference | Requested bidder answer | Cost/programme effect | Responsible party | Status |
|---|---|---|---|---|---|
| Drawing or schedule discrepancy | Document number and revision | Written interpretation or required change | To be stated | Buyer / bidder | Open |
| Panel or interface assumption | Panel mark or detail | Included, excluded, or allowance | To be stated | Bidder | Open |
| Material alternative | Schedule line | Proposed product and deviation | To be stated | Bidder / design team | Open |
| Testing responsibility | Test schedule | Method, agency, report, retest | To be stated | Project team / bidder | Open |
| Delivery or installation boundary | Logistics/site schedule | Exact responsibility allocation | To be stated | Buyer / bidder | Open |
How Do You Compare Unitized Curtain Wall Bids on the Same Scope?
Level a bid before interpreting its price. Compare the same document basis, facade scope, panels, glass/infill, materials, engineering, BIM, testing, QA/QC, factory work, logistics, installation, commercial terms, assumptions, alternatives, exclusions, and open issues.
Same-scope bid-leveling matrix:
| Category | Buyer baseline | Bidder response | Status | Assumption or deviation | Cost/programme effect | Clarification |
|---|---|---|---|---|---|---|
| Project and documents | Issue list and revisions | Documents used | Confirm | Missing or conflicting data | To be stated | Open/closed |
| Facade scope | Areas, elevations, non-unitized zones | Scope covered | Confirm | Area or interface assumption | To be stated | Open/closed |
| Panels | Panel schedule, quantities, repetition | Panel basis | Confirm | Custom or unique panels | To be stated | Open/closed |
| Glass/infill | Approved schedule | Proposed make-up | Confirm | Alternative or substitution | To be stated | Open/closed |
| Materials/finish | Profiles, finish, hardware | Product basis | Confirm | Equal or alternative | To be stated | Open/closed |
| Engineering/BIM | Responsibility matrix | Deliverables | Confirm | Revision allowance | To be stated | Open/closed |
| Testing/QA | Test and mockup brief | Plan and reports | Confirm | Retest or agency assumption | To be stated | Open/closed |
| Factory scope | Assembly, glazing, inspection | Factory activities | Confirm | Storage or rework | To be stated | Open/closed |
| Logistics | Delivery and site boundary | Logistics basis | Confirm | Customs, unloading, or lifting | To be stated | Open/closed |
| Installation | Labor, supervision, handover | Installation scope | Confirm | Site adjustment or replacement | To be stated | Open/closed |
| Commercial | Currency, validity, tax, payment | Terms | Confirm | Allowance or exclusion | To be stated | Open/closed |
A lower total is not a better offer until missing scope, alternatives, allowances, taxes, duties, logistics, installation, and assumptions have been reconciled.
Common Unitized Curtain Wall RFQ Mistakes to Avoid
- Issuing drawings without revision status or an addenda register
- Providing elevations without a panel/module schedule
- Using "double glazing" or "high performance" without a defined glass/infill basis
- Omitting corners, transitions, openings, non-typical panels, and interface details
- Mixing supply-only, delivered, and installed pricing in one comparison table
- Leaving engineering, BIM, testing, mockups, QA/QC, and submittal responsibilities unstated
- Assuming factory assembly includes all packaging, storage, shipping, or site handling
- Omitting customs, duties, taxes, unloading, lifting, storage, and replacement responsibility
- Allowing bidders to price different delivery points or programmes
- Comparing a base bid against an offer with unmarked alternatives or allowances
- Accepting a supplier's "included" statement without a line-item scope
- Assuming the lowest lump sum is the lowest complete scope
FAQ: Unitized Curtain Wall RFQ Questions Buyers Ask
What should be included in a unitized curtain wall RFQ?
Include a controlled project brief, drawing and revision register, elevations and details, panel/module schedule, glass and infill schedule, materials and finishes, performance and testing requirements, responsibility matrix, factory and logistics scope, delivery and installation boundaries, programme, commercial assumptions, and a standard supplier response format.
What drawings does a unitized curtain wall supplier need to quote?
Provide current elevations, grids, plans, sections, typical and non-typical details, corners, transitions, slab edges, parapets, roof and base conditions, interfaces, specifications, revision register, and addenda. Identify missing information and ask bidders to list the documents used for their response.
What information does a curtain wall manufacturer need for an RFQ?
The manufacturer needs enough information to understand the project, package boundary, panel schedule, materials, performance brief, engineering scope, factory work, delivery point, installation boundary, programme, and commercial assumptions. The required detail depends on the design stage and procurement route.
How should glass requirements be written in a curtain wall RFQ?
Use a glass and infill schedule that states make-up, thickness, coatings, interlayers, spacer or gas assumptions where relevant, dimensions, visual criteria, samples, performance targets, approved alternatives, factory-glazing responsibility, storage, and replacement assumptions.
Should installation be included in a unitized curtain wall quotation?
Only when the RFQ clearly defines the installation boundary. State whether labor, supervision, lifting, site adjustments, training, replacement, re-delivery, handover, and technical support are included, excluded, optional, or subject to confirmation.
What should a unitized curtain wall supplier response include?
Bid identification, scope confirmation, pricing schedule, status matrix, technical response, programme, assumptions, qualifications, clarifications, and document list. Every bidder should use the same categories so omissions and deviations are visible.
How do I compare unitized curtain wall bids on the same scope?
Normalize the document revision, facade scope, panel schedule, glass/infill, materials, engineering, testing, factory work, logistics, installation, commercial terms, alternatives, exclusions, and assumptions. Record open questions and reconcile them before interpreting the totals.
What are common mistakes when preparing a curtain wall RFQ?
Uncontrolled revisions, missing panel schedules, vague glass descriptions, omitted custom or interface conditions, mixed supply and installation boundaries, unstated testing or engineering scope, different delivery points, and unmarked alternatives or allowances.
Conclusion: Control the Inputs, Then Compare the Offers
A well-prepared unitized curtain wall RFQ gives every bidder the same reviewable basis. The practical sequence is:
- Define the brief and package boundary. State the project, procurement route, quotation type, contacts, deadline, and included work.
- Control the technical information. Issue current drawings, revisions, elevations, details, panel schedules, material schedules, performance requirements, and testing information.
- Normalize the responses. Require line-by-line inclusions, exclusions, alternatives, assumptions, clarifications, programmes, documents, and responsibility boundaries before comparing totals.
Send Your Unitized Curtain Wall RFQ to FOWALL
Preparing a unitized curtain wall RFQ? Send FOWALL your project location, building type, drawings, elevations, panel/module schedule, glass and infill requirements, performance targets, delivery point, installation boundary, and programme.
Our team will return a project-specific quotation using the included/optional/excluded/confirm format above, with assumptions, clarifications, and logistics terms stated line by line. We also support factory inspections by you or your appointed third-party inspector.
Structural, code, performance, fire, testing, installation, and acceptance requirements should be confirmed by qualified project professionals using project documents and applicable requirements.