Are Mockups and Testing Included in a Unitized Curtain Wall Quote?

Sep 17,2026

Why “Testing Included” Is Not Enough

A unitized curtain wall quotation may say “testing included,” “mockup included,” or “QA/QC provided.” Those phrases are useful starting points, but they do not identify the complete activity, specimen, configuration, project basis, agency, witness, report, responsible party, retesting route, or record package.

Test / QA itemSpecimen / basisAgency / witnessReport / statusRetest / correctionScope / owner

This article assumes that a quotation has been returned. It focuses on whether mockups, tests, inspections, witnessing, reports, retesting, corrective work, factory/site checks, and related records are explicitly disclosed. It does not design a test, choose acceptance values, interpret a code, approve engineering, or decide whether a project has passed.

Direct Answer: Are Mockups and Testing Automatically Included?

No. Mockups, testing, and QA/QC are not automatically included in every unitized curtain wall quote. Ask the supplier to list each activity separately and classify it as:

IncludedOptionalExcludedSubject to ConfirmationOpen Question

Each line should also identify the specimen or configuration, project-document basis, agency or witness, report or record, responsible party, review route, and treatment of retesting or corrective work.

A record is not a universal conclusion.A test report, witness sign-off, factory release, QA/QC record, or “passed” label does not automatically establish project approval, code compliance, certification, performance, final acceptance, or contractual completion.
Controlled drawings used to define mockup configuration, test basis, revisions, and records
Testing scope should be tied to a controlled specimen, configuration, drawing or model revision, project basis, responsible parties, and record route.

Laboratory and Field/Site Mockups

Laboratory pre-construction mockups

A laboratory mockup may examine a representative portion of a proposed exterior wall system, depending on project documents. ASTM E2099-23 describes pre-construction laboratory mockup specification and evaluation. That source-scoped description does not create a universal requirement, price, schedule, or acceptance result.

  • Is the mockup Included, Optional, Excluded, Subject to Confirmation, or Open Question?
  • What configuration, materials, glazing/infill, interfaces, and details does it represent?
  • Which drawing/model revision and approved configuration form the basis?
  • Who provides specimen materials, fabrication, assembly, glazing, sealing, and changes?
  • Who coordinates the agency and witness?
  • Which observations, data, photographs, reports, checklists, and transfers are included?
  • Who coordinates changes, corrective work, retesting, and revised reporting?

Field/site mockups

A field or site mockup may expose constructability, sequence, interference, tolerances, interfaces, and site conditions not represented in a laboratory. ASTM E3223/E3223M-20 addresses field-constructed exterior-wall mockups and expressly notes that project roles and obligations should be documented.

  • Is it separate from the laboratory mockup?
  • Where will it be built?
  • Which substrate and interfaces does it represent?
  • Who provides access and temporary protection?
  • Which observations and records are included?
  • Which project-defined status applies afterward?

Representative configuration

For either mockup type, connect the specimen to panel or assembly identification; drawing/model revision; glass, infill, aluminum, gaskets, sealants, anchors, hardware, and finishes; openings or interface conditions; location and support conditions; intended observation, testing, or documentation scope; and record holder and handover destination.

The project team should define what the specimen represents and what it does not represent. A representative description is not a universal performance statement, and one mockup should not be presented as representing every facade condition.

Test Scope, Project Basis, and Agency Responsibilities

Project basis and method reference

Each test line item should identify the project specification, test brief, inspection and test plan, approved configuration, contract requirement, or other project-defined basis. A quote may reference ASTM E331-00(2023), AAMA/FGIA 501.4-18, AAMA/FGIA 501.7-17, or another method where referenced by project documents. This article does not select applicability or set acceptance values.

ASTM E331 describes water-penetration testing under a uniform static air-pressure difference and notes that results can depend on installation, adjustment, support construction, thermal movement, vibration, and other conditions. AAMA/FGIA 501.4-18 and 501.7-17 describe method contexts for specified horizontal or vertical inter-story movement evaluations. These references support questions about method, specimen, configuration, support conditions, and reporting; they do not make a test automatically applicable, sufficient, passed, or compliant.

Test agency, inspector, and witness

ASTM E329-21 addresses inspection/testing agency personnel, facilities, equipment, quality systems, responsibilities, methods, records, reports, review, and transmission of findings. The quotation and project documents should state:

  • agency or inspector appointment and scope;
  • test or inspection method and project basis;
  • witness role and limitations;
  • specimen/configuration information;
  • data, report, photograph, and checklist deliverables;
  • report review, response, and status route;
  • retest, corrective-work, and revised-report responsibilities; and
  • record holder and handover format.

A witness signature, agency report, or inspection record is a project record with defined scope. It does not by itself establish final acceptance, code compliance, certification, contractual completion, or performance for the whole project.

Reports and review/status

Identify whether reports are prepared, reviewed, transmitted, revised, or archived under the quoted scope. Ask whether the supplier provides data where required, photographs, checklists, nonconformance or corrective-action records, comment/response logs, revised reports, and a final record index.

Report issued and Reviewed are workflow or documentation statuses. They should not be treated as automatic approval or final acceptance.

Factory Inspection and Factory Glazing/Sealing Checks

A testing and QA/QC quotation should separate incoming, in-process, factory-glazing/sealing, dimensional, labeling, packaging/protection, and factory-release checks. Factory glazing does not automatically remove every site inspection requirement.

Incoming material and component checksGlass, infill, aluminum and finish recordsAssembly and dimensional checksGlazing and sealing checksCompatibility or adhesion documentsLabels and panel identificationNonconformance and corrective recordsTransfer to contractor/site team

The exact checks, formats, sampling, timing, and responsible parties depend on project documents and applicable professional or QA/QC requirements. This article does not prescribe a universal inspection plan.

Factory Release

Define what Factory Release means for the project. It may be a production or documentation status associated with a panel or batch, but it is not automatically site receiving, installation approval, final acceptance, certification, code compliance, or contractual completion.

FOWALL publicly describes categories including incoming material verification, in-process quality control, functional testing, final audit, project labeling, packaging/protection, and document requests. These public process descriptions support quotation questions; they do not prove that a specific quote includes every check or that a process guarantees project quality.

Facade manufacturing facility representing factory inspection, release, labeling, and record scope
Factory activities should be separated into incoming, in-process, glazing/sealing, dimensional, labeling, packaging, release, and record-transfer items.

Site Receiving, Site Glazing, and Installation-Related Checks

Site-side QA/QC may include receiving condition, labels, package damage, storage/protection, site glazing/sealing, installation observations, and records. Whether these activities are included depends on the quotation, installation scope, project QA/QC documents, and assigned parties.

  • Who performs site receiving and records damage or shortage?
  • Who checks labels and panel/configuration identity?
  • Who provides storage and protection and records pre-installation condition?
  • Is site glazing included, and who checks glass, gaskets, sealants, and interfaces?
  • Are installation-related observations or checklists included?
  • Who records adjustments, nonconformance, corrective action, replacement, and reinspection?
  • Which records are part of the test/QA-QC handover package?

This is a scope clarification section, not an installation method or acceptance guide. Factory release does not automatically substitute for site receiving, installation-related checks, or final project review.

Unitized curtain wall buildings illustrating representative facade configurations and project conditions
A representative test or inspection configuration should identify the actual panels, interfaces, support conditions, materials, revisions, and limits it covers.

Retesting, Corrective Work, and Change Control

A quotation should disclose the process for changes after a report, observation, or nonconformance. Keep cost, programme, testing, logistics, installation, and documentation effects To be confirmed until project documents and responsible parties establish them.

Trigger / reportAffected specimenRevision / correctionAgency / witnessRetest / reinspectionRecord / handover

Request fields for the triggering observation, report, or comment; affected specimen, configuration, panel, location, or work area; drawing, model, material, or method revision; proposed correction or rework; responsible coordinator and reviewer; agency, witness, report, or reinspection route; project-defined retest requirement; revised quotation, change, or addendum reference; effects marked To be confirmed; and status and record route.

Do not say retesting is free, included, automatically attributable to one party, or guaranteed to produce a particular result without project-specific documentation.

Status Taxonomy

Quotation scope

IncludedOptionalExcludedSubject to ConfirmationOpen Question

Workflow / project

Open / Submitted / ReturnedRevised / ReviewedProfessional reviewResponsibility to assignRecord

Test / inspection

Specimen preparedTest scheduled / performedReport issuedComment/response openRetest / Corrective work

Project status

Factory ReleaseSite ReceivingFinal Acceptance

These families are project-defined and must not be interchanged. A report, witness sign-off, Reviewed, Factory Release, Site Receiving, or Test performed status is not automatically an approval, code-compliance conclusion, certification, final acceptance, or contractual-completion conclusion.

Test and QA/QC Scope Matrix

Use exactly these quotation scope labels: Included, Optional, Excluded, Subject to Confirmation, and Open Question.

Test / QA itemSpecimen / configurationProject basis / method referenceAgency / witness / reportResponsible partyRetest / corrective-work fieldQuotation status
Laboratory mockupRepresentative unitized configuration, materials, interfaces, locationProject brief, specification, test planTo assignParties to assignTo be confirmedOne of five labels
Field/site mockupLocation, sequence, substrate/interface, representative conditionProject documents and approved briefTo assignParties to assignTo be confirmedOne of five labels
Test activityConfiguration and scope; no method/value selection hereProject-defined test basisAgency/data/report routeParties to assignTo be confirmedOne of five labels
Incoming inspectionMaterials/components and recordsProject QA/QC documentsInspector/record routeParties to assignTo be confirmedOne of five labels
In-process/factory checksAssembly, glazing, sealing, dimensional, labelingFactory procedure and project documentsRecords/review routeParties to assignTo be confirmedOne of five labels
Factory releasePanel status, release record, document packageProject-defined release routeReviewer/status to assignParties to assignTo be confirmedOne of five labels
Site receiving/site checksDamage, labels, storage/protection, receiving recordsSite QA/QC and delivery documentsInspector/record routeParties to assignTo be confirmedOne of five labels
Retest/corrective workRevised specimen/affected work and change recordProject change/test processAgency/witness/report to assignParties to assignTo be confirmedOne of five labels
Test/handover recordsReports, photos, checklists, corrective records, statusHandover/project requirementsDocument controller/reviewerParties to assignTo be confirmedOne of five labels

This is a quotation-disclosure tool. It does not design tests, set acceptance values, assign legal responsibility, define performance, or prove project compliance.

Mockup/Test Responsibility Matrix and Inspection Checklist

The status column is intentionally named Status / role field / open item. Responsibility to assign is a role-allocation field; the five quotation labels are scope labels; Open Question is an unresolved quotation item.

ActivityProject-defined owner / design roleContractorSupplier / fabricatorInstallerTest agency / inspectorQA/QC / document controlStatus / role field / open item
Mockup brief/configurationRole to assignCoordinate as assignedProvide data/samples as assignedSite input if requiredReview/perform as appointedRecord routeResponsibility to assign
Mockup preparationParty to assignCoordinate/accessFabricate/assemble if includedInstall if includedObserve/perform if appointedRecordsSubject to Confirmation
Test appointment/witnessingProject-defined roleCoordinateSupport as statedSupport accessPerform/witness/reportRecord/report routeResponsibility to assign
Factory inspection/releaseProject-defined roleReview/coordinatePerform/record if included—Inspect if appointedMaintain recordsSubject to Confirmation
Site receiving/checksProject/site roleCoordinateProvide records/supportCheck/install as assignedInspect if appointedRecord statusResponsibility to assign
Retesting/corrective workReview/change roleCoordinateCorrect/rework if includedReinstall/adjust if includedRetest/report if appointedRecord changesSubject to Confirmation
Test/handover recordsDefine requirementsCompile/coordinateProvide factory recordsProvide site recordsProvide reportsIndex/submit/storeOpen Question

Inspection checklist

  • Is factory inspection classified with one of the five scope labels?
  • Are incoming material/component checks identified?
  • Are assembly, glazing, sealing, dimensional, and labeling checks identified?
  • Are panel labels, factory release, and release records defined?
  • Is packaging/protection inspection included or separately assigned?
  • Are site receiving, damage, storage, and protection checks included?
  • Are factory glazing and site glazing separated, including labor, materials, inspection, and records?
  • Are installation-related observations included without recreating installation scope?
  • Who records nonconformance, correction, replacement, reinspection, and re-delivery?
  • Which reports, photographs, checklists, and handover records are included?
  • Which items remain Subject to Confirmation, Open Question, Professional review, or Responsibility to assign?

Roles must be assigned through project documents and applicable appointments. This matrix is not a universal allocation.

Clarification Questions Before Award

  1. Are laboratory and field/site mockups separately listed?
  2. What specimen, configuration, materials, interfaces, and location does each represent?
  3. Which project document, test brief, specification, or approved configuration forms the basis?
  4. Which test methods are referenced, and who confirms applicability?
  5. Who appoints and coordinates the agency, inspector, or witness?
  6. Which reports, data, photographs, checklists, and records are included?
  7. What review/status route applies to a report or witnessed activity?
  8. Are retesting, changed specimens, corrective work, rework, replacement, reinspection, and re-delivery separately stated?
  9. Are incoming, in-process, glazing/sealing, dimensional, labeling, and release checks included?
  10. Are site receiving, site glazing, protection, and installation-related checks included?
  11. Which items use each of the five quotation scope labels?
  12. Who coordinates the register and retains the project record?
  13. Which cost, programme, testing, logistics, installation, and handover effects remain To be confirmed?

FAQ: Mockups, Testing, and QA/QC in Quotations

Are mockups included in a unitized curtain wall quote?

Not automatically. Ask whether laboratory and field/site mockups are separate line items, then confirm the specimen, configuration, materials, interfaces, location, basis, agency/witness, reports, retesting, corrective work, and records.

Is curtain wall testing included in the quotation?

The word “testing” is not enough. Ask which activity, specimen, basis, agency, witness, report, review route, retest/corrective-work treatment, responsible party, and quotation status are included.

What is the difference between laboratory and field mockups?

A laboratory mockup is prepared in a controlled setting described by project documents; a field/site mockup is constructed at or for the site and may involve site interfaces, sequence, access, and local conditions. The project must define purpose and represented configuration.

Who appoints the curtain wall test agency or witness?

The appointing party should be identified in project documents, quotation, responsibility matrix, or applicable appointment. Confirm who coordinates agency, witness, report, review, response, retest, and record routes.

Who pays for curtain wall retesting or corrective work?

Do not assume the answer. Ask project and quotation documents to identify coordination, correction, rework, retesting, reinspection, replacement, re-delivery, and commercial effects. Keep unresolved effects To be confirmed.

Are factory and site inspections included in curtain wall pricing?

Not automatically. Separate incoming, in-process, factory glazing/sealing, dimensional, labeling, factory-release, site-receiving, site-glazing, protection, and installation-related checks, with a status and responsible party for each.

Does factory glazing change the testing and QA/QC scope?

It may change which checks and records occur at the factory or site, but no universal allocation should be assumed. Separate factory glazing/sealing, packaging/protection, receiving, site glazing, installation checks, and handover records.

Does a curtain wall test report prove project approval or compliance?

No automatic conclusion should be drawn. A report has a defined specimen, configuration, method, conditions, data, and review route. Project professionals and documents determine how it is reviewed and whether it supports a separate status or acceptance decision.

Conclusion and Project-Specific CTA

Mockups, testing, inspections, witnessing, reports, retesting, corrective work, factory/site checks, and QA/QC records should be itemized in a quotation rather than hidden behind “testing included.”

  1. Separate the activities. List laboratory mockups, field/site mockups, tests, inspections, witnesses, reports, retesting, corrective work, factory/site checks, and records.
  2. Define the basis. Link each item to the specimen/configuration, project documents, method reference, approved configuration, and interfaces.
  3. Assign the route. Name the agency, witness, responsible party, reviewer, record holder, and retest/corrective-work coordinator.
  4. Separate statuses. Keep quotation scope labels apart from workflow, test/inspection, and project statuses.
  5. Record unresolved effects. Keep cost, programme, testing, logistics, installation, documentation, and handover effects To be confirmed.
  6. Obtain professional review. Route test selection, acceptance criteria, design, contract, code, installation, QA/QC, and final acceptance to qualified professionals.

Share the quotation, mockup brief, test schedule, inspection and test plan, approved configuration, responsibility matrix, report requirements, and handover list for a project-specific mockup, testing, and QA/QC scope review.

FOWALL’s public pages describe categories such as engineering review, material verification, in-process quality control, testing, final audit, labeling, packaging/protection, and document requests. Any service availability, scope, fee, test activity, report, technical responsibility, or deliverable must be confirmed for the specific project. This article does not provide test design, test results, approval, compliance, performance, quality, price, delivery, or supplier-capability conclusions.