What Should Be Included in a Unitized Curtain Wall Quotation?
Introduction: "Included" Must Be Written in the Quotation
A unitized curtain wall quotation should be reviewed as a project-specific scope and commercial document, not only as a lump-sum number. The word included has meaning only when the supplier identifies the relevant product, deliverable, responsibility, document basis, and commercial boundary in writing.
A useful unitized curtain wall quotation should disclose its project reference and revision basis, system and material scope, glass and infill, engineering and technical documents, testing and QA/QC, factory work, packaging and logistics, delivery and installation boundaries, commercial terms, alternatives, allowances, assumptions, exclusions, and open clarifications.
Ask the supplier to mark each line as Included, Optional, Excluded, Subject to Confirmation, or Open Question. Scope varies by project, procurement route, contract boundary, and written assumptions, so this guide is a review framework rather than a universal inclusion list.
This is the third guide in our unitized curtain wall buying series. Our pricing guide explains which project variables change a quotation, and our RFQ checklist explains what to prepare before requesting bids. This guide starts later: it explains what a supplier's returned quotation should disclose.
What Should a Unitized Curtain Wall Quotation Disclose?
Before interpreting the total, check whether the quotation addresses the following sections:
| Quotation section | What the supplier should disclose | Status to request |
|---|---|---|
| Identity and basis | Project/package, quotation number, revision, issue date, validity, currency, quantity basis, delivery point, and referenced documents | Subject to Confirmation / Open Question |
| System and materials | System configuration, profiles, reinforcement, thermal breaks, gaskets, sealants, anchors, hardware, finishes, and accessories | Included / Optional / Excluded / Subject to Confirmation |
| Glass and infill | Glass make-up, spandrel, metal panel, opaque infill, openings, transitions, and alternatives | Included / Optional / Excluded / Subject to Confirmation |
| Engineering and documents | Calculations, shop/fabrication drawings, BIM, revisions, submittals, manuals, and responsible party | Included / Optional / Excluded / Subject to Confirmation |
| Testing and quality | Samples, mockups, tests, witnessing, reports, retesting, QA/QC, traceability, and handover records | Included / Optional / Excluded / Subject to Confirmation |
| Factory work | Assembly, glazing, sealing, inspection, labeling, storage, rework, replacement, and release | Included / Optional / Excluded / Subject to Confirmation |
| Logistics | Packaging, loading, shipping, customs, insurance, delivery, unloading, storage, lifting, and damage responsibility | Included / Optional / Excluded / Subject to Confirmation |
| Installation and handover | Labor, supervision, training, adjustments, replacement, re-delivery, manuals, and handover support | Included / Optional / Excluded / Subject to Confirmation |
| Commercial terms | Taxes, duties, payment, escalation, alternatives, allowances, validity, assumptions, qualifications, and exclusions | Included / Optional / Excluded / Subject to Confirmation |
| Open items | Missing information, deviations, qualifications, unresolved questions, and response date | Open Question |
Supply-only, delivered-to-site, technical-support, design-assist, delegated-design, and installed quotations can have very different boundaries, so read every line against the quotation type.
Quotation Identity and Commercial Basis
Project and Package Reference
The quotation should identify the issuing entity, project name, package or elevation reference, RFQ number, quotation number, revision, issue date, and clarification contact. It should be clear which legal or trading entity is making the offer. Do not assume that the issuing entity, manufacturer, factory, carrier, and installer are the same party.
Revision, Validity, and Document Basis
Ask which drawings, specifications, schedules, addenda, clarification responses, and quantities were used. The quotation should state its validity period and the conditions that could change the offer after that period. A quotation based on an earlier revision may not cover the same scope as one based on a later revision.
Quantity, Delivery, and Commercial Basis
Check whether the offer is based on a lump sum, unit rates, stated quantities, provisional items, or another basis. Review the currency, tax and duty treatment, delivery point, quotation type, payment assumptions, escalation, and validity provisions. Your procurement documents and contract review govern how these terms apply.
System, Aluminum, Glass, Infill, Finishes, and Hardware Scope
Base System and Aluminum Components
The supplier should identify the quoted system family or configuration, glazing method, glass plane, system depth or other relevant product parameters, and the documents supporting the description. The quotation should separately identify, as applicable:
- Aluminum profiles and reinforcement
- Thermal breaks, isolators, gaskets, and sealants
- Anchors, brackets, fasteners, flashings, pressure plates, cover caps, and hardware
- Drainage, closure, interface, and accessory items
- Finishes, colors, gloss, texture, samples, and batch requirements
- Work by others or components outside the quoted package
The screening fields on our Unitized Curtain Wall Systems page (glazing method, glass plane, infill, system depth, and performance categories) are a practical checklist for confirming the basis of any quotation.
Glass and Infill
The quotation should state the proposed glass and infill basis rather than relying on a product name or a broad phrase such as "double glazing." Check for:
- Glass make-up, nominal thickness, coatings, interlayers, spacers, and gas assumptions where relevant
- Insulated, laminated, monolithic, spandrel, metal-panel, opaque, stone, or other infill
- Openings, vents, doors, fins, shading, corners, transitions, and non-unitized areas
- Visual criteria, color, frit, reflectance, ceramic coating, samples, and mockup status
- Approved alternatives, substitutions, and differences from the specified basis
The quotation should state whether glass procurement, factory glazing, storage, breakage allowance, spare units, replacement, and site protection are included. If the glass basis is incomplete, mark it Subject to Confirmation or Open Question rather than treating it as included.
Finishes, Accessories, and Alternatives
The supplier should identify the finish system and material assumptions. Proposed alternatives should be listed separately from the base offer, with product data, sample status, technical differences, responsibility, and any effect on the rest of the quotation.
Engineering, Drawings, BIM, Submittals, and Revisions
Technical scope should be itemized rather than hidden under "technical support." Ask whether the quotation includes or excludes:
- Design-assist or delegated design
- Calculations and project analyses
- System and interface details
- Shop and fabrication drawings
- Material schedules and bills of materials
- BIM model authoring, coordination, file exchange, and revisions
- Samples and submittal registers
- Responses to review comments and revision limits
- Installation instructions or method information
- Maintenance and handover documentation
The quotation should name the responsible party for each deliverable and state the assumed number or boundary of revisions. A general statement that engineering or BIM is "available" does not explain whether the service is included, separately priced, optional, or subject to confirmation.
Our Curtain Wall Design & Budget Planning service covers engineering, shop drawings, calculations, BIM, material schedules, installation planning, manufacturing, and logistics coordination. Whichever supplier you use, ask for each of these to be listed as its own line with a status.
Testing, Mockups, QA/QC, Traceability, and Handover Documents
Samples, Mockups, and Tests
The quotation should state the scope and status of samples, mockups, laboratory or field tests, witnessing, reports, retesting, corrective work, and final submissions. Ask the supplier to identify the method, specimen or configuration, test agency, report format, acceptance criteria, and responsible party.
ASTM E2099-23 covers pre-construction laboratory mockups for exterior wall systems, and ASTM E331-00(2023) covers water-penetration testing of curtain walls under a uniform static air-pressure difference. A cited standard describes a test method; it does not by itself mean the test is included in the quotation or that the project will pass.
QA/QC and Traceability
Check whether the quotation includes factory inspection points, release criteria, material and batch traceability, finish and color checks, dimensional inspections, nonconformance records, rework, replacement, packaging inspection, and site acceptance records.
Handover Records
If handover documents are required, the quotation should identify format, responsible party, and delivery status for items such as:
- Approved product data and final schedules
- As-built drawings and models
- Installation and maintenance manuals
- Test and inspection reports
- Material certificates and traceability records
- Sample and finish records
- Nonconformance and corrective-action records
- Spare or replacement-unit records
- Training or handover sign-off documents
Factory Assembly, Factory Glazing, and Release Scope
The phrase "factory assembled" can cover different activities. The quotation should mark the status of:
- Assembly and pre-assembly
- Factory glazing and sealing
- Inspection and release
- Labeling and panel identification
- Storage before dispatch
- Rework, repair, and replacement units
- Packaging inspection
- Batch traceability
- Allowable site adjustments
- The boundary between factory QA/QC and site acceptance
FOWALL's unitized panels are factory-glazed, so the release point between factory and site is a natural line to confirm in writing. Whichever supplier you use, mark a factory activity Included only when the project-specific quotation expressly covers it.
Packaging, Shipping, Customs, Delivery, and Site Handling
A quotation should make the logistics boundary visible across the supplier, carrier, buyer, and site team. Check whether it states:
- Packaging type and protection for glass, corners, fins, and custom units
- Loading and containerization
- Shipping, insurance, and loss/damage responsibility
- Customs, duties, and taxes
- Delivery point, port, and inland route
- Unloading and site storage
- Weather protection and damage inspection
- Lifting equipment, hoist/crane interface, and floor access
- Site handling and staging
- Replacement, re-delivery, and claims procedures
The delivery point should show exactly where supplier responsibility ends and buyer, carrier, or site responsibility begins. An Incoterm should be read together with the actual quotation scope and contract; it does not answer every site-handling question on its own.
Installation, Supervision, Technical Support, and Handover
Supply-only, delivered-to-site, technical-support, and installed quotations are not the same scope. The supplier should state whether the offer includes:
- Installation labor
- Site supervision
- Training or installation guidance
- Lifting and access coordination
- Site adjustments
- Replacement units and re-delivery
- Protection and cleaning
- Testing support
- As-built documents and maintenance manuals
- Handover assistance
- Work by others or excluded adjacent packages
If installation is not included, the quotation should still state whether technical support, instructions, supervision, training, site visits, or installation-interface coordination are available and on what basis.
Alternatives, Allowances, Assumptions, Qualifications, and Exclusions
A transparent quotation separates its base offer from everything that is not part of the confirmed base scope.
Base Offer and Alternatives
The base offer should identify the system and material basis used for the quoted scope. Proposed or approved alternatives should be listed separately, including the affected line item, product data, technical difference, status, and any responsibility or programme implication. An unmarked substitution should not silently replace the specified basis.
Allowances and Provisional Items
An allowance should state what it covers, the quantity or basis assumed, who controls the final selection, and what remains variable. If unit rates or provisional items are provided, identify their limits and the conditions under which they apply.
Assumptions and Qualifications
Ask the supplier to list assumptions about drawings, dimensions, quantities, interfaces, design responsibility, testing, delivery, installation, access, storage, taxes, duties, programme, and information still required. Qualifications should identify any deviation from the RFQ or referenced documents.
Exclusions and Work by Others
Each exclusion should identify the affected scope and, where known, the responsible party or required follow-up. An exclusion is a boundary to clarify or assign, not evidence that the supplier cannot perform the work.
Scope-of-Supply Disclosure Template
Use this template to request a structured response from each supplier.
Status legend:
- Included: expressly covered by the quotation
- Optional: available only if separately selected or priced
- Excluded: expressly outside the quoted scope
- Subject to Confirmation: mentioned or expected but not confirmed in writing
- Open Question: requires clarification before the scope is understood
| Quotation line | Supplier response | Status | Responsible party | Supporting document/assumption | Open clarification |
|---|---|---|---|---|---|
| Quotation identity | Project, package, revision, date, validity, currency, quantity basis | Subject to Confirmation / Open Question | Supplier / buyer | Quotation and referenced documents | Response date |
| System and materials | System, profiles, reinforcement, thermal breaks, gaskets, sealants, anchors, hardware, finishes | Included / Optional / Excluded / Subject to Confirmation | Supplier / design team | BOM and scope schedule | Open Question |
| Glass and infill | Glass make-up, spandrel, metal panel, opaque infill, openings, alternatives | Included / Optional / Excluded / Subject to Confirmation | Supplier / design team | Glass/infill basis | Open Question |
| Engineering/documents | Calculations, shop/fabrication drawings, BIM, revisions, submittals | Included / Optional / Excluded / Subject to Confirmation | Named party | Deliverables list | Open Question |
| Testing/quality | Samples, mockups, tests, witnessing, reports, retesting, QA/QC, traceability | Included / Optional / Excluded / Subject to Confirmation | Named party | Test/QA schedule | Open Question |
| Factory work | Assembly, glazing, sealing, inspection, labeling, storage, rework, release | Included / Optional / Excluded / Subject to Confirmation | Supplier / factory | Factory scope | Open Question |
| Logistics | Packaging, loading, shipping, customs, insurance, delivery, unloading, storage, lifting | Included / Optional / Excluded / Subject to Confirmation | Supplier / buyer / carrier | Delivery boundary | Open Question |
| Installation/support | Labor, supervision, training, adjustments, replacement, re-delivery, handover | Included / Optional / Excluded / Subject to Confirmation | Named party | Installation/support scope | Open Question |
| Commercial terms | Taxes, duties, payment, escalation, alternatives, allowances, service wording | Included / Optional / Excluded / Subject to Confirmation | Supplier / buyer | Commercial schedule | Open Question |
| Open issues | Assumptions, exclusions, deviations, qualifications, missing information | Open Question | Named party | Clarification register | Response date |
What Are the Warning Signs of an Incomplete Quotation?
Treat these as prompts for clarification rather than judgments about the supplier:
- A lump-sum total with no project, quotation number, revision, or validity
- No document list or unclear drawing/specification basis
- A product name without a configuration, glass/infill, or material schedule
- No distinction between Included, Optional, Excluded, Subject to Confirmation, and Open Question
- Engineering or testing described only as "support" with no deliverables
- No statement of factory glazing, sealing, inspection, or release scope
- Delivery described only as "shipped" with no delivery point, unloading, or customs boundary
- Installation described only as "available" or "supported" with no labor or supervision boundary
- Alternatives or allowances embedded without separate identification
- No assumptions, qualifications, exclusions, or open-question register
- Warranty, lead-time, certification, or performance wording without project-specific documents and written terms
For each gap, ask the supplier to state the status, responsible party, document basis, and commercial or programme effect.
FAQ: Unitized Curtain Wall Quotation Questions Buyers Ask
What should be included in a unitized curtain wall quotation?
The quotation should disclose its project and revision basis, system and material scope, glass and infill, engineering and technical documents, testing and QA/QC, factory work, logistics, installation and handover, commercial terms, alternatives, assumptions, exclusions, and open questions, each marked with a status for the specific project.
Are glass and aluminum profiles automatically included in a curtain wall quote?
Not automatically. The quotation should identify the glass/infill make-up, profiles, reinforcement, thermal breaks, finishes, accessories, substitutions, and exclusions. If the basis is not confirmed, mark it Subject to Confirmation or Open Question.
Does a unitized curtain wall quote include engineering and shop drawings?
Only if the supplier states the deliverables, responsible party, revision scope, and commercial status. A general "technical support" phrase does not define whether calculations, shop drawings, BIM, submittals, or revisions are included.
Are mockups and testing included in a curtain wall quotation?
Ask the supplier to identify the mockup and test method, specimen or configuration, agency, witnessing, reports, retesting, and corrective-work scope. A cited standard describes a method; it does not make the test part of the quotation.
Does a unitized curtain wall quotation include packaging and shipping?
Review packaging, loading, shipping, insurance, customs, duties, delivery point, unloading, storage, lifting, damage, replacement, and re-delivery responsibility in writing. "Delivered" or "shipped" alone may not define the full logistics boundary.
Is installation included in a unitized curtain wall quotation?
Check whether labor, supervision, training, lifting, site adjustments, replacement, re-delivery, handover, and maintenance documents are Included, Optional, Excluded, Subject to Confirmation, or Open Question. Supply-only and installed scopes are not identical.
How should curtain wall quotation exclusions be listed?
Each exclusion should identify the affected work, relevant document or line item, responsible party where known, and the clarification or follow-up required.
What assumptions should a curtain wall supplier disclose?
Assumptions about drawings and revisions, quantities, system and material basis, interfaces, engineering, testing, factory work, delivery, customs, unloading, installation, access, storage, programme, taxes, duties, alternatives, and information still required. Record unresolved assumptions as Open Question before considering the quotation further.
Conclusion: Read the Scope Before the Total
A unitized curtain wall quotation should show more than a total. You should be able to identify:
- What the supplier has priced: the project basis, system, materials, glass, infill, engineering, testing, factory work, logistics, installation, and handover.
- What is outside the confirmed base scope: alternatives, allowances, qualifications, exclusions, work by others, and unresolved assumptions.
- What still needs written clarification: status, responsible party, supporting document, and any commercial or programme effect.
Get a Line-Item Unitized Curtain Wall Quotation from FOWALL
Reviewing a unitized curtain wall quotation, or about to request one? Send FOWALL your project reference, drawings or quotation revision, delivery point, installation boundary, technical requirements, and open questions.
We will return a project-specific scope schedule that marks each line as Included, Optional, Excluded, Subject to Confirmation, or Open Question, so you can compare it directly with other offers. We also support factory inspections by you or your appointed third-party inspector.
Technical, structural, code, performance, testing, installation, tax, customs, and contract decisions should be confirmed by qualified professionals using project documents.